Olympic pool to be used for water polo competitions and other water disciplines at the Aquatics Center on the island of Gozo, Malta.
The pool will be 50 m x 25 m in size and its depth will be between 2.2 m and 3 m. The system chosen for the project is Skypool, Fluidra's patented technological solution, which consists of prefabricated hot galvanized steel panels fixed to a concrete block, covered with PVC-P coating.
Besides the Olympic pool, the center will have a multi-purpose public pool and will be adjacent to another sports complex, which is currently under development and will have other ancillary facilities, including a 500m2 gym and a first aid room.
* System Construction Areas of Responsibility
-13,670 m2 Reinforced Concrete Construction Area
-3.880 m2 Open Construction Area
-360 tons Steel Works
-All Waterproofing Works
-All M&E Jobs,
-Prefabricated Paneled Olympic Swimming Pool
-3 Squash Courts
-Basketball court
-Multi-Purpose Gymnastics Areas
-SPA Facilities