Olympic pool to be used for water polo competitions and other water disciplines at the Aquatics Center on the island of Gozo, Malta.

The pool will be 50 m x 25 m in size and its depth will be between 2.2 m and 3 m. The system chosen for the project is Skypool, Fluidra's patented technological solution, which consists of prefabricated hot galvanized steel panels fixed to a concrete block, covered with PVC-P coating.

Besides the Olympic pool, the center will have a multi-purpose public pool and will be adjacent to another sports complex, which is currently under development and will have other ancillary facilities, including a 500m2 gym and a first aid room.

* System Construction Areas of Responsibility

-13,670 m2 Reinforced Concrete Construction Area

-3.880 m2 Open Construction Area

-360 tons Steel Works

-All Waterproofing Works

-All M&E Jobs,

-Prefabricated Paneled Olympic Swimming Pool

-3 Squash Courts

-Basketball court

-Multi-Purpose Gymnastics Areas

-SPA Facilities

  • Location
    Gozo - Malta
  • Duration
    17.03.2020 - 14 Month
  • Status
    Completed
  • Client
    The Ministry for Gozo of the Goverment of Malta