SUPPLYING HIGH VOLTAGE SHORE CONNECTION (HVSC) SYSTEM USING ENERGY EFFICIENT EQUIPMENT IN THE GREAT PORT OF VALLETTA


MALTA


The project allows cruise ships and cargo ships to shut down their kerosene or heavy fuel oil engines while docked and plug in shore electricity to power their onboard systems.


Project scope


-Construction of Frequency Converter Station buildings ( FCS 1 and FCS 3)


-33kV supply to FCS1 and FCS3 buildings from Marsa North DC


-Two lengths of 33kV submarine cable and communication/fiber optic cable installation


- Supply and installation of all 11 kV cables


-100 mm heavy-duty PVC duct, communication cable and fiber optic cable (50 mm HDPE inside duct) supply and installation


-Construction of a fairly long culvert and canal bank


-High-level steel support structure


-Provision of LV/ELV systems


-Restoration of historical building (including facing stone, culverts, steel structure, interior walls, roofing)


-Providing asphalt works


-Operation of the HVSC system at five berths for two years


-Design, supply, installation, testing and commissioning of the following equipment


33kV gas insulated input distribution boards.


33kV, 24 pulse input rectifier transformers


Supply transformers of auxiliaries


SFCs complete with refrigeration equipment


rectifier output transformers


Rectifier transformer output 11 kV gas insulated switchgear


11kV RLC filter switch


Switchgears related to neutral grounding resistances of galvanic isolation transformers


11 /6.6kV galvanic isolation transformers and their associated pre-magnetization transformers and voltage regulation equipment.


Ship junction boxes on land


shore-to-ship mobile cable management equipment


8 passenger elevators


auto start standby generator


1 OV DC system batteries

  • Yer
    Valletta, Malta
  • Süre
    03.06.2020 - 30 Ay
  • Durum
    Devam Eden
  • İnşaat Alanı
    Kıyı Bağlantısı, İnşaat ve Restorasyon İşleri
  • Müşteri
    Altyapı Bakanlığı Malta